Honka USA Process Timeline

Building a Honka Home, Step by Step

Twenty steps from your budget and land to delivery day, in eight phases, with typical costs and timing for each.

A note before you start

I learned the value of a roadmap the hard way.

In 1995 I was so eager to start my first home that I bought five wooded acres at 10,000 feet on Conifer Mountain, Colorado, on impulse. Only afterward did I learn it was the highest price ever paid for a lot on that mountain.

I took a 12-line budget to the bank, got approved and started building. About four months in, I realized my construction loan was hundreds of thousands of dollars short of what it would really take to finish the home.

It was a hard lesson: look before you leap. The timeline below is the roadmap I wish I'd had. Walk through it before you sign anything.

Mark Jermano, Principal, Honka USA

Phase 1

Your Turnkey Budget, and Your Land

Two numbers to set before anything else.

Step 1

Establish Your Total Turnkey Budget

Your turnkey budget combines land, construction, all professional fees, permits and financing.

As a rule of thumb, land should be no more than about 25% of the total.

We estimate construction costs from total square footage, finished and unfinished, because size drives cost in home building. A master bath costs more than a garage, but total cost divided by total square feet is a reliable place to start.

Honka homes typically come in around $400 to $600 per sq ft with basic site development, not including land or financing. Site work and finishes can move that number a lot, and the Honka Budget Pricing Tool lets you adjust for both.

Aerial view of a green Colorado mountain valley with a lake, homes among the pines and a highway along the river
Land and home: two budgets, set first.

Step 2

Purchase Land

Without land it's difficult to place the home for solar orientation, or to locate the garage, the drive and the view corridors.

Still looking? Our Honka Real Estate Service offers inexpensive professional consulting for land buyers.

Most people buy land with only an Improvement Location Certificate (ILC). An ILC isn't a real survey; it only estimates your approximate boundaries. An ALTA survey typically runs $1,800 to $3,500

A smiling couple in a pine forest, the woman riding piggyback on the man's shoulders
Finding the right piece of land.
Phase 2

Shaping the Design to Your Lot

Two paths to a design. Both end in a factory model your bank and builder can use.

Step 3A

Gallery Model Modification

Modify an existing Honka model to fit your lot and the way you live.

  • Concept site plan about $500
  • Floor plan modifications $500 to $1,000

Usually completed in less than 10 days.

In more than 24 years we've never built a Honka model exactly as drawn. Every one has been modified to fit its owner and its lot. Find your starting point in the Honka model gallery.

Rendering of the standard Honka Sirius 126 model: a single-story home with yellow siding and a small covered entry
The Honka model: Sirius 126.
The same Sirius 126 modified for a client's lakeside lot: natural wood siding, a wide entry canopy and a drive among the pines
Modified for the owner and the lot.

…or

Step 3B

Custom New Design from Scratch

Create a custom design from scratch with an architect, shaped to your lifestyle, lot and vision. $1,000 to $5,000

  • Includes a conceptual site plan, floor plans, elevations, roof plan and sections.
  • If needed, a landscape architect can add a detailed site plan with spot grades, drainage, culverts, road design and retaining walls. + about $1,000
Steve Young's Honka home in Park City, Utah at dusk: glowing windows, solid timber walls, stone piers and a curved wraparound deck above the snow
The Young home at dusk, Park City, Utah.
The architect's pencil sketch of the south elevation of Steve Young's Honka home in Park City, Utah
The first sketch: south elevation.
Conceptual site plan of Steve Young's Honka home in Park City, Utah: the home's footprint, the drive and the limits of disturbance drawn over the slope's contour lines
The conceptual site plan: the home placed on the slope, with the drive and limits of disturbance.
The finished south side of Steve Young's Honka home in Park City, Utah: solid timber walls, arched windows, stone piers and a wraparound deck
The same side, built: NFL Hall of Famer Steve Young's Honka home in Park City, Utah.

Step 4

Factory Model

What the factory model does for you:

  • Lets you see the home from the inside out, room by room.
  • Gives you a working document to adjust as you learn more about the site.
  • Shows local builders, lenders and vendors you have a real project, not just an idea.

Dimensioned floor plans, sections and 3D exterior elevations of the structure. $1,000 to $2,500

Add photorealistic interior renderings. + about $500

We can also model your site topography (trees, rocks, water) for a truer picture of the actual setting and views. + $1,000 to $3,500 This depends on having topographic information from a survey (see Step 2).

Factory model exterior rendering of a modern Honka home with a deck and a car in the drive
The factory model your bank and builder will use.
Factory model interior rendering of a modern Honka home: a bright great room and kitchen with floor-to-ceiling windows
An interior rendering.
Phase 3

What Comes from Finland

The components, their share of your budget, and the deposit that starts production planning.

Step 5

Honka Component Pricing

We price the components made in our plant in Finland:

  • Log walls
  • Structural posts and beams
  • Windows
  • Lift-and-slide doors
  • Pre-finished interior doors and hardware
  • Interior casing
  • Exterior siding and soffit
  • Interior ceiling paneling

Depending on your selections and the size of the home, Honka components typically run 30% to 50% of your total turnkey budget.

Bright Honka interior with pale solid timber walls and ceiling, black window frames and a view to the lake
Walls, windows, doors and paneling, made in Finland.

Step 6

Start Production Planning

A 25% deposit secures the raw materials, schedules engineering and starts pre-production planning.

By this point the construction documents for permit are final, so the structure's engineering can be reviewed by both our US engineers and our engineers in Finland.

A planning team reviews a production schedule on a large screen in a modern office
Engineering and pre-production planning.
Phase 4

Your Builder and Your Bank

You don't need a "log home builder." Here's who you do need.

Step 7

Builder Selection and Contract

Finding a good local builder is the most important step in moving your project forward. They bring the local vendor base that makes for better budgets.

Look for a competent, trustworthy builder with solid referrals and a history of finished projects in your community. We train the builder's crew and can also provide an on-site supervisor.

A builder in a hard hat and safety vest reviews plans with a homeowner inside a timber home under construction
Your local builder, trained on the Honka system.

Step 8

Builder Conceptual Budget

Most builders offer a small pre-construction services agreement so they're paid for your initial budgeting.

Expecting this step for free usually leads to unrealistic numbers later.

We also work with a nationwide builder who prepares conceptual construction budgets for our projects for a small fee. It gives you a baseline to measure local bids against, so you can vet potential builders and walk into those conversations already knowing the numbers.

Builder budget report for a custom home, line by line: preliminary phase (survey, architectural plans, structural, septic and soils engineering, insurance, permits, interior design) and preparation phase (site work, well, excavation, fill, drains, septic, foundation, structural steel, waterproofing, driveway), with estimated costs and totals
A real builder budget, line by line: the preliminary and preparation phases.

Step 9

Construction Loan Appraisal (if financing)

Give your bank the factory model (Step 4) and the builder's conceptual budget (Step 8). That starts the appraisal, which sets the loan-to-cost and loan-to-value for your project.

Most lenders require at least 25% down in cash or equity.

A hand filling out a real estate appraisal form on a clipboard
The bank's appraisal starts here.
Phase 5

Construction Plans and Permits

What the county needs before you can build. Honka USA provides the complete stamped construction documents through permit.

Step 10

Construction Documents

We provide a complete set of construction documents for permitting on every Honka project, anywhere in the US. See where we're building.

If you choose to start the process without us, typical fees are:

  • Architectural set about $6 to $8 per sq ft
  • Structural engineering, by an engineer licensed in your state about $2.50 to $3 per sq ft
  • Energy-code analysis (ResCheck) of the log walls, windows, insulation and heating and cooling about $1,200
  • Soils report, if your soil needs it $2,000 to $3,500

We set the basic design criteria for your lot from the ASCE Hazard Tool. The factory model (Step 4) is great for budgeting, but it doesn't carry code details like insulation values, stair dimensions, lighting and power plans or window U-values. That's what this set adds.

Architectural drawings on a drafting table with pencils, a ruler and a protractor
Architectural, Structural & Mechanical Engineering Provided
The ASCE Hazard Tool website, used to look up the wind, snow and seismic design criteria for a building site
ASCE design criteria
Two hands holding a sample of soil from a building site for a soils report
Soils Report: Soil Bearing Capacity Determines the Foundation Design
A REScheck energy code compliance certificate for a log home in Clear Creek County, Colorado, showing it passes
Energy Code Compliance: Honka Homes Exceed Energy Requirements in Difficult Jurisdictions Like Aspen

Step 11

Building Permits and HOA Approvals

Permits are issued once the architectural and structural sets meet the jurisdiction's requirements. Some counties also want a grading permit first, drawn by a local civil engineer. about $2,500

In a platted subdivision, the HOA or architectural review committee has its own submittal, usually about materials and colors (wood, stone, metal roofing and so on). a few hundred to a few thousand

A building permit stamp pressed onto construction drawings beside rolled blueprints
Building permits.
A yellow warning sign reading HOA Fees on a weathered wood wall
The HOA review, if you have one.
Phase 6

Real Numbers, and Closing the Loan

With full plans, your builder can bid the whole job.

Step 12

Final Builder Bid

With a full set of construction documents, your builder can bid the entire project, so you know your costs to within a few percent.

Finishes like tile, countertops, flooring, lighting and plumbing fixtures are still allowances at this stage.

Finishes can be the most stressful part of a project, because your selections directly shape the final look and feel of the home. We've worked with interior designers all over the US.

The best ones aren't cheap, but they're well worth the fee: they coordinate the whole home so color, texture, warmth and style carry through every room.

Page from a detailed final construction budget with line items and totals
A full bid, line by line.

Step 13

Construction Loan Closing

With a final budget and building permits in hand, your bank is ready to close the construction loan.

Most community banks issue a construction loan and later a permanent loan; any US lender can take out the construction loan once the home is finished. Some banks offer construction-to-permanent from the start, but interest then accrues on the full amount right away.

A couple shakes hands with a banker across a table after closing their loan
Closing the construction loan.
Phase 7

Ordering Your Honka

Shop drawings, the final order, and your production slot.

Step 14

Update the Factory Model to Match the Plans

Any changes in the final construction documents go into an updated factory model, so every component is made to the final engineering. No charge for this step.

Rendering of a Honka great room with solid log walls, a stone fireplace, an open stair and globe pendant lights
The model, updated to the final plans.

Step 15

Update the Order and Shop Drawings

We reconcile the order up or down, so you pay only for exactly what is produced.

Then come the shop drawings: every wall elevated and every row labeled, with electrical drillings added from your lighting and power plans. Our architecture and engineering team coordinates the shop drawing review with Finland.

Honka shop drawing of a log wall elevation with every row labeled and dimensioned
A shop drawing: every row, labeled.

Step 16

Book Your Production Slot

With the updated factory model and shop drawings approved and the 75% balance funded, your production slot is secured, about five to six weeks out.

Close-up of a cutting head milling a pale laminated timber log in the Honka plant
Precision milling in Finland.
Phase 8

Site Work, Shipping and Delivery Day

Your foundation goes in while Finland builds your home.

Step 17

Start Site Work

Excavation, foundation, well and septic, underground plumbing and flatwork can all happen while your components are made in Finland.

Depending on the design, the first framed subfloor and any stick-framed garage walls can go up too.

Excavated building site with foundation footings in sandy soil, ringed by pine trees on a mountain slope
Foundation work on a mountain site.

Step 18

Ship Your Honka

Your package is produced and loaded into containers in less than a day.

Transit to the nearest US port takes about six to eight weeks, depending on weather.

Wrapped Honka timber bundles, labeled HONKA, stacked on a trailer and ready to ship
Bundled, labeled and ready to ship.

Step 19

Clear Customs and Schedule Delivery

Under current customs rules, all tariffs are paid before the goods are released. We estimate these early, but they can change.

Our shipping agents then manage delivery from the port to your site, working directly with you or your builder, typically in 7 to 10 days.

Cranes unloading shipping containers from a cargo ship at a US port
From the port to your site.
A worker opens a shipping container of wrapped Honka bundles at the building site
Opening the container on site.

Step 20

Unload the Containers

Schedule the right equipment once the product is released from port: typically a crane and a 10,000 lb telehandler.

Each container should be unloaded within about two hours to avoid extra charges. The video shows every step of getting the bundles out of the containers.

A truck delivers a container of Honka bundles to a snowy site, and the wrapped bundles are pulled out of the container
Delivery day.

That's It: 20 Steps to the Starting Gate

We're looking forward to building your home with you, one step at a time.