Step 1
Establish Your Total Turnkey Budget
Your turnkey budget combines land, construction, all professional fees, permits and financing.
As a rule of thumb, land should be no more than about 25% of the total.
We estimate construction costs from total square footage, finished and unfinished, because size drives cost in home building. A master bath costs more than a garage, but total cost divided by total square feet is a reliable place to start.
Honka homes typically come in around $400 to $600 per sq ft with basic site development, not including land or financing. Site work and finishes can move that number a lot, and the Honka Budget Pricing Tool lets you adjust for both.